Market data · East Bank of the Cumberland River · Status as of Nov. 12, 2026

The New Nissan Stadium and the East Bank

Crews are finishing the Titans' enclosed stadium beside the Cumberland on the East Bank. A team representative told the East Bank Development Authority in September 2026 that full substantial completion is set for Feb. 17, 2027, and the team's own site says opening is anticipated in 2027. Concerts are booked for summer 2027 and the NFL has awarded the building Super Bowl LXIV in February 2030. Below, each confirmed fact carries its source and date, followed by the decisions a rental owner faces because of it.

Key facts
Status, Nov. 12, 2026
Under construction; opening anticipated in 2027 (Titans)
Early turnover areas
Jan. 7, 2027 (Titans representative, reported Sept. 23, 2026)
Full substantial completion
Feb. 17, 2027 (same report)
Seats
About 60,000
Roof
Enclosed, translucent ETFE, not retractable
Cost and public share
About $2.1 billion; $1.26 billion in state and Sports Authority bonds
Concerts announced
Kenny Chesney July 3, 2027; Morgan Wallen Aug. 27 and 28, 2027
Super Bowl LXIV
February 2030, awarded May 19, 2026
On this page
  1. What the Titans are building
  2. Construction status and the dates on record
  3. Events already booked for 2027
  4. Super Bowl LXIV in 2030
  5. How the stadium is paid for
  6. The 1% hotel tax that short-term rental guests pay
  7. What the team projects
  8. The old stadium and the land it frees
  9. The East Bank district around it
  10. The hotel that will open after the Super Bowl
  11. Getting to the stadium from downtown
  12. What an owner should do now
  13. Questions
  14. Sources

What the Titans are building

The team's stadium page describes an enclosed building of about 60,000 seats, smaller than the current Nissan Stadium, on land just east of it. The roof is a circular, translucent ETFE design and will not open. The field is artificial turf, and the plan includes a 12,000-square-foot community center.

Besides the Titans, the team names TSU football and other sports, shows and civic gatherings as tenants, and it pitches the building as big enough for a Super Bowl, a Final Four, a playoff game in college football or a WrestleMania. The team's page says the building will have less on-site parking than the current stadium, with partner lots, public transit and rideshare filling the gap.

Construction status and the dates on record

No source we opened gives an exact opening day. The Titans' site says only that opening is anticipated in 2027. The firmest dates come from WKRN's Sept. 23, 2026 report on an East Bank Development Authority meeting, where a Titans project representative said early turnover areas are scheduled for Jan. 7, 2027 and full substantial completion for Feb. 17, 2027. The same report put about 2,300 workers on site each day and about 10,000 seats installed, with the ETFE roof due by mid-October and a test of all 2,100 plumbing fixtures at once planned for November.

Later reporting shows the work moving. StadiumDB wrote on Oct. 14, 2026 that more than 19,000 seats were in by the end of September, the ETFE cladding was about half installed and the ring of LED video board was about 80% complete, and it described the opening as spring 2027. NewsChannel 5 reported in September 2026 that major events and concerts are expected to begin in April 2027. Per a May 2026 Tennessean story, crews broke ground Feb. 29, 2024 and set the last steel beam Nov. 21, 2025.

Events already booked for 2027

Three concert dates, for two acts, were on record by Nov. 12, 2026. Kenny Chesney's Original Vibe Room Tour plays the new stadium on July 3, 2027, with Greylan James opening, according to NewsChannel 5. The Tennessean reported on Nov. 12, 2026 that Morgan Wallen will close his 2027 Last Time I Checked Tour with two nights there, Aug. 27 and 28, 2027, and that Zach Bryan and Noah Kahan are also among the first acts booked.

The same Tennessean report says the current stadium closes after the 2026-27 NFL season. We found no announced first event for the new building. Treat any earlier date as unconfirmed until the Titans or the promoter announce it.

Super Bowl LXIV in 2030

League owners meeting in Orlando picked Nashville for Super Bowl LXIV on May 19, 2026, according to a WZTV timeline of the deal, the first time the city will host the game. The Titans wrote the next day that it will take place in February 2030 at the new stadium. Neither source gave the exact day.

WSMV wrote on Sept. 22, 2026 that roughly half a million people are expected around the game. For scale, it quoted the Nashville Downtown Partnership's directory: some 67 lodging properties downtown holding near 14,100 rooms. Expect the event week to be sold out across downtown and priced well above a normal February.

How the stadium is paid for

The Bond Buyer reported on April 26, 2023 that the Metro Council approved the deal after a five-hour hearing, with construction estimated at $2.1 billion. Metro's Sports Authority issues $760 million of revenue bonds, the state sells $500 million of general obligation bonds, and the team brings $840 million raised from seat licenses and league money. The team agreed to a 30-year lease and to pay off $30 million of outstanding bonds on the old stadium.

The Titans' page says property taxes are not part of the financing and that the team is responsible for any cost overruns. It lists the public side as sales tax collected in the stadium, a portion of sales tax from the surrounding campus, an added 1% hotel occupancy tax in Davidson County and a state contribution. The Bond Buyer named the 1% hotel tax and the in-stadium sales tax as what repays the Sports Authority bonds.

The 1% hotel tax that short-term rental guests pay

With BL2022-1529, passed Dec. 20, 2022, Metro put one more percentage point on its occupancy tax, which Metro Finance began collecting July 1, 2023. Since then the local occupancy levy has been 7%; the flat nightly charge stayed at $2.50, and Metro Finance's posted return still uses that figure. Finance's notice says the extra point reaches every hotel or similar place housing transients. Its monthly return for rental owners was reissued in a new version for tax due after that date.

In practice, every permitted rental night in Nashville helps repay the stadium bonds. Quote guests the all-in total, and use our occupancy tax guide to work out each bill.

What the team projects

The Titans publish their own economic projections, and they are the team's estimates rather than independent findings. For construction, the team projects more than 19,000 full- and part-time jobs, $1.9 billion in one-time direct spending and $3.0 billion in total economic impact. Over 30 years of operation, it projects $20.9 billion in direct spending, $33.7 billion in total impact and 4,927 jobs a year, and says the city's planned neighborhood on returned land will bring more than $1 billion to the general fund in its first 30 years.

The old stadium and the land it frees

The deal returns riverfront land to Metro, and the Titans' page says the city plans a neighborhood there with mixed-income housing, green space and retail. The timing of demolition differs by source. WKRN reported in September 2026 that work is expected to begin around March 2027, after the last game, and that the old stadium will be taken apart mechanically rather than imploded because it stands about 95 feet from the new one. StadiumDB wrote in October 2026 that demolition is expected in 2028 and that the site will become parking and open public space. Plan for disruption on that side of the campus through at least 2027.

The East Bank district around it

Metro describes the East Bank as a 550-acre area along the Cumberland River, from I-24 in the south to River North and the planned Oracle campus in the north, and nearly 10 times the size of the Gulch. Metro owns about 130 acres, including the stadium land. Its blueprint, the Imagine East Bank plan, came out of two years of Planning Department public work and won a unanimous Planning Commission vote in October 2022.

The Fallon Company was chosen in September 2023 to develop the first 30 city-owned acres, and the Council's April 2024 vote on its contract was unanimous. In June 2024 the Council created the East Bank Development Authority to oversee the work. Planning added a 30-acre East Bank subdistrict to the Downtown Code. TPAC and Metro signed a memorandum of understanding that would move the performing arts center to Parcel E, beside the pedestrian bridge. Metro is also gathering comments on a planned north-south spine called East Bank Boulevard.

The hotel that will open after the Super Bowl

A 600-room hotel by The Fallon Company is planned next to the new stadium. WSMV reported on Sept. 22, 2026 that the game will come first and the hotel later. Ground is now expected to break around July 2027, with guests arriving in summer 2030. The authority's board weighed building through the game while limiting construction disruption, putting up a parking garage first, or pausing until after the Super Bowl.

For owners, that means no large new hotel on the East Bank before the game, and a large one arriving soon after. Downtown and nearby permitted units carry the overflow until then.

Getting to the stadium from downtown

StadiumDB reports that the stairs on the south side are designed as the entry for many fans walking in over the Seigenthaler bridge. With less on-site parking than today, guests staying within walking distance of the bridge have an advantage on event days. Say so in the listing only if it is true of your unit, and give the actual route.

What an owner should do now

  • Add each confirmed stadium date to the pricing calendar as soon as it is announced, starting with July 3 and Aug. 27 and 28, 2027.
  • Treat Super Bowl week in February 2030 as a separate pricing and minimum-stay decision, and decide it early.
  • Before buying near the stadium for nightly rental, pull the parcel's zoning and confirm it with Metro Codes. Metro grants new permits for units the owner does not occupy only in certain named districts, and DTC East is excluded.
  • Plan for event-night noise, crowds and street closures in the house rules and the arrival instructions.
  • Watch the East Bank Development Authority's meetings, where dates for the hotel, the boulevard and demolition are reported first.

Questions

Has the new Nissan Stadium set an opening day?

The Titans say opening is anticipated in 2027. A team representative gave Jan. 7, 2027 for early turnover areas and Feb. 17, 2027 for full substantial completion, WKRN reported on Sept. 23, 2026. NewsChannel 5 reported that major events are expected from April 2027. No first event had been announced by Nov. 12, 2026.

What concerts are booked at the new stadium?

Kenny Chesney on July 3, 2027, and Morgan Wallen on Aug. 27 and 28, 2027. The Tennessean also named Zach Bryan and Noah Kahan among the first acts booked, without dates in the report we opened.

Who paid for the new stadium?

Per The Bond Buyer, the roughly $2.1 billion splits three ways: Sports Authority bonds of $760 million, state bonds of $500 million, and $840 million on the Titans' side from seat licenses and the league. The team's page says it covers any overruns.

Do short-term rental guests pay toward the stadium?

Yes. An extra point of occupancy tax, collected since July 1, 2023, goes toward the Sports Authority's bonds, and Metro levies it on short stays of every kind, rentals included. Metro takes 7% of the bill, and its current return form adds $2.50 a night. A 2026 ordinance pushes back the end date for part of that nightly charge, so check the figure with Metro Collections before you quote it.

Is the Fallon hotel going to open before the 2030 game?

No. WSMV reported on Sept. 22, 2026 that the 600-room hotel is slated to start construction around July 2027 and open in summer 2030, after the February 2030 game.

Could a building beside the stadium be permitted for nightly stays?

Zoning decides it, parcel by parcel. A unit the owner will not live in can get a new permit only in a district Metro Code names; DTC East is off that roster, and a specific plan parcel follows whatever its own plan says. Every apartment is permitted separately. Get Metro Codes to confirm before signing a contract.

Sources

  1. Tennessee Titans, New Nissan Stadium project information, opened Nov. 12, 2026
  2. WKRN (via Yahoo Sports), New Nissan Stadium set for February 2027 completion, Sept. 23, 2026
  3. StadiumDB, Two NFL stadiums side by side, Nissan Stadium nearing completion, Oct. 14, 2026
  4. NewsChannel 5, Kenny Chesney announces 2027 concert at Nashville's new Nissan Stadium (September 2026)
  5. The Tennessean (via Yahoo), Morgan Wallen to play two nights at new Nissan Stadium in 2027, Nov. 12, 2026
  6. The Tennessean (via Yahoo Sports), When will Nashville's new Nissan Stadium open, May 18, 2026
  7. WZTV (via WLOS), Timeline of Nashville's stadium push and Super Bowl LXIV, May 19, 2026
  8. Tennessee Titans, Nashville, Titans, NFL celebrate Super Bowl LXIV coming to Music City, May 20, 2026
  9. WSMV, Flagship hotel in Nashville won't be ready in time for Super Bowl 2030, Sept. 22, 2026
  10. The Bond Buyer, Bonds will fund majority of $2.1 billion stadium for NFL's Tennessee Titans, April 26, 2023
  11. Metro Finance, Increase of Hotel Occupancy Tax, June 14, 2023 (Wayback copy, Oct. 23, 2026)
  12. Metro Finance, Pay Short Term Rental Property Occupancy Tax (updated Jan. 5, 2026; Wayback copy, Oct. 22, 2026)
  13. Metro Nashville, East Bank Development (Wayback copy, Oct. 23, 2026)
  14. Metro Nashville, East Bank Development, What Should I Know (updated May 20, 2024; Wayback copy, Oct. 22, 2026)
  15. Metro Code 6.28.030, short term rental property permits (Municode, current through June 23, 2026)
  16. Metro Finance, Short-Term Rental Tax return (510), taxes payable after July 1, 2023, line "Number of rooms rented per night x $2.50" (archived copy, October 22, 2026)
  17. Metro Council, BL2026-1493, passed Sept. 1, 2026, Mayor approved Sept. 4, 2026; Section 4 moves the 5.12.140 B date, Section 10 sets the effective date (Legistar)

Checked November 12, 2026.